As at 6 February 2024, the contractor had improved its performance, with earthworks almost complete on this section, which stretches from Welcome to Bamenda to _Ecole des champions_. Generally speaking, Bofas, the contractor in charge of works on this 4.9 km section, has undertaken to complete earthworks and concentrate on the carriageway.
Earthworks now cover a distance of 4.5 km / 4.9 km, and prefabricated T2+CS2 kerbs have been constructed on 4.350 km. Of the 6.188 km of concrete ditches, the contractor has already laid 1 km and prefabricated for 2.700 km. With regard to hydraulic structures, 20 are envisaged: 6 have been completed and several are prefabricated. Of the 2,171 km of GBA guardrails expected, 1,208 km are prefabricated. However, it should be noted that works on related projects have not yet started on this lot. They concern the development of 7 km of secondary roads, namely: Nsanemeka-Hotspot, Cattle Market - Mutangoh and Akumbele - Bamendankwe Fons's Palace.
0 commentaire(s)
Laissez un commentaire
Votre adresse électronique ne sera pas publiée. Les champs obligatoires